Removal of Temporary Bridges

We have received notification of works to remove temporary bridges over the river. DX49 which is the last bridge to be removed located up stream of the old PowerStation at Richborough which was due for removal week commencing 7th June. This date has been postponed and is now scheduled that the decking of the bridge will be removed week commencing 28th June with a duration of 3 working days. The bridge will then be lifted out on the week commencing 5 July duration of works 1-2 working days.

Murphy Richborough OHL Connection project apologies for any inconvenience this change causes